Operations strategy Revision notes

Unit 4: Operations management · Chapter 28 · about 16 minutes · written for the 9609 syllabus · last checked 2026-11-17

Operations strategy is about making the production of goods and services as efficient, flexible and reliable as possible over the long term. This chapter covers the tools the syllabus names: enterprise resource planning, lean production and critical path analysis. CPA calculations appear regularly in Paper 3, and Paper 4 asks you to evaluate a business’s operations strategy over several years.

Operational decisions

Operations decisions (what to produce, how, where and in what quantity) depend on the other functions’ resources:

  • Human resources: the number and skills of workers decide which methods are possible; a highly automated process needs fewer but more skilled staff.
  • Marketing: forecast demand and customers’ expectations of quality, price and delivery decide the output needed and how flexible it must be.
  • Finance: the money available decides whether the business can invest in new equipment, technology or capacity.

IT and AI in operations

Technology now runs much of operations: computer-aided design and manufacturing (CAD/CAM), robots and automated warehouses, sensors that predict machine breakdowns, AI that plans production and forecasts demand, and real-time tracking of inventory and deliveries. Benefits are higher productivity, consistent quality and better decisions; drawbacks include high investment and training costs, job losses and staff resistance, cyber-security risks and dependence on systems.

Flexibility and innovation

Customers increasingly expect variety and speed, so operations need flexibility in:

  • Volume: raising or cutting output quickly as demand changes (using flexible contracts, overtime or spare capacity);
  • Delivery time: meeting short or changing delivery deadlines;
  • Specification: adapting products to individual customers’ requirements.

Process innovation: changing current production processes or adopting new ways of producing goods or delivering services, for example automation, 3D printing or self-service technology.

Process innovation can cut costs, raise quality and speed up production, but needs investment, retraining and careful management of change.

Enterprise resource planning (ERP)

Enterprise resource planning (ERP): a single computer system that links all the main functions of a business (purchasing, inventory, production, sales, finance and HR) using one shared database, so that information is updated across the whole business in real time.

When a customer places an order, an ERP system can check inventory, schedule production, order materials, plan staff, invoice the customer and update the accounts automatically. It can improve efficiency in:

  • Inventory control: exact, real-time stock levels and automatic reordering, so less inventory is held.
  • Costing and pricing: accurate costs for each order or product, so prices can be set to ensure a profit.
  • Capacity utilisation: production is scheduled to make the best use of machines and staff.
  • Responses to change: managers see changes in demand or supply at once and can adjust plans quickly.
  • Workforce flexibility: staff can be allocated to where they are needed.
  • Management information: accurate, up-to-date data for decision-making.

Limitations: very expensive to buy and install; long, disruptive implementation; staff need training and may resist; the business may have to change its processes to fit the software; and the system depends on accurate data input.

Lean production

Lean production: producing goods and services with the minimum of wasted resources (materials, time, labour, space and inventory) while maintaining high quality.

Its aims are to reduce waste and costs, raise quality and productivity, shorten the time taken to produce and deliver, and respond more flexibly to customers.

MethodHow it works
Kaizen (continuous improvement)Many small, regular improvements suggested by employees, rather than occasional big changes
Quality circlesSmall groups of workers meet regularly to identify and solve quality and production problems
Simultaneous engineeringProduct development tasks (design, testing, production planning, marketing) are carried out at the same time rather than one after another, cutting the time to launch
Cell productionThe production line is split into self-contained teams (cells), each making a complete unit or part of the product and responsible for its quality
Just-in-time (JIT) manufacturingMaterials arrive just when needed and products are made to order, so little or no inventory is held
Waste managementIdentifying and removing every kind of waste: over-production, waiting, unnecessary movement, defects, excess inventory

Links and limitations

Lean production is closely linked to inventory control (JIT minimises stock), quality (defects are waste, so quality must be built in, as in TQM), employees’ roles (multi-skilled, empowered workers in teams), capacity management (output matched to demand) and efficiency overall.

Limitations: JIT depends on very reliable suppliers, so a single disruption can stop production; there is no buffer stock for sudden rises in demand; the change in culture takes time and needs staff commitment; training and reorganisation are costly; and some lean methods suit large-scale manufacturing better than small or service businesses.

Operations planning: network diagrams and CPA

Large projects (building a factory, launching a product, installing a system) involve many activities, some of which must follow others. A network diagram shows the order of the activities and their durations, and is used for critical path analysis (CPA).

  • Activities are shown as arrows, labelled with a letter and duration.
  • Nodes (circles) mark the start and end of activities. Each shows its number, its earliest start time (EST) of the next activities and the latest finish time (LFT) of the activities before it.
  • Dummy activities (dotted arrows with no duration) show that one activity depends on another when the arrows alone can’t show it.
A network diagram for a project with seven activities. The critical path A, C, E, G takes 14 days, the minimum project duration; activities B, D and F each have 4 days of total float A 4 B 3 C 5 D 2 E 3 F 6 G 2 1 0 0 2 4 4 3 3 7 4 9 9 5 12 12 6 14 14 In each node: number (left), earliest start time (top right), latest finish time (bottom right). Durations in days.
Activities on the critical path (A, C, E, G) are shown in the first colour: any delay to them delays the whole project.

Working it out

  1. EST (forward pass): start at 0; each node’s EST is the EST of the previous node plus the activity’s duration. Where two activities end at a node, take the larger figure. Node 4: C gives 4 + 5 = 9, D gives 3 + 2 = 5, so EST = 9.
  2. Minimum project duration = the EST of the final node: 14 days.
  3. LFT (backward pass): the final node’s LFT equals its EST; each earlier node’s LFT is the next node’s LFT minus the duration. Where two activities start at a node, take the smaller figure. Node 2: C gives 9 − 5 = 4, F gives 14 − 6 = 8, so LFT = 4.
  4. Critical path: the activities with no float, where EST = LFT at both ends and the timings fit exactly: A → C → E → G.

total float = LFT (end node) − duration − EST (start node)

free float = EST (end node) − duration − EST (start node)

Activity B: total float = 7 − 3 − 0 = 4 days; free float = 3 − 3 − 0 = 0 days. Activity D: total float = 9 − 2 − 3 = 4 days; free float = 9 − 2 − 3 = 4 days. Activity F: total float = 14 − 6 − 4 = 4 days.

Total float is how long an activity can be delayed without delaying the whole project. Free float is how long it can be delayed without delaying the next activity. B can slip by 4 days without delaying the project, but any delay to B uses up D’s float.

Using CPA in project management

  • Managers know the minimum time the project will take and can give customers a reliable completion date.
  • They focus supervision on critical activities, since any delay there delays everything.
  • Resources can be moved from activities with float to critical ones if problems arise.
  • Materials can be ordered to arrive when needed (supporting JIT), and parallel activities can run at the same time to save time.

Limitations: durations are estimates and can be wrong; drawing and updating complex networks takes time (though software helps); it plans time, not cost or quality; and it doesn’t guarantee the plan will be followed. Rushing to meet critical deadlines can also hurt quality.

Answering the Paper 3 and 4 questions

Typical questions: “Calculate the total float for activity C” or “Complete nodes 5 and 6 on the network diagram” (Paper 3); “Analyse two likely benefits to RR of introducing lean production”; “Evaluate the effectiveness of KK’s operations strategy between 2020 and 2024”; or “Evaluate how significant ERP was to CH’s operations strategy” (Paper 4).

Papers 3 and 4 mark long answers on knowledge, application, analysis and evaluation, and “Analyse” questions stop before evaluation. Plan every long answer in the same five steps, in this order:

  1. Knowledge: define the tools in the question: ERP, lean production and its methods, flexibility, process innovation, critical path, total and free float.
  2. Application: use the case: the business’s products, operations problems (waste, late deliveries, high inventory, quality), resources, and its results over time. Complete any CPA calculations accurately, showing working.
  3. Analysis: build chains: for example, JIT cuts inventory, freeing working capital and storage space, so costs fall and cash flow improves, but it makes production depend on reliable suppliers.
  4. Evaluation: weigh benefits against costs and risks for this business: supplier reliability, staff training and attitudes, the investment needed, the time to see results, and whether the method suits its size and type of production.
  5. Conclusion: make a justified judgement, for example: ERP was highly significant to the business’s operations strategy because it cut inventory and late deliveries, although its cost meant the benefits took three years to show in profit.

Check yourself

What does ERP stand for, and how can it improve inventory control?

Enterprise resource planning: a shared, real-time system that shows exact stock levels and reorders automatically, so less inventory is held.

What is kaizen?

Continuous improvement through many small, regular changes, usually suggested by employees.

Give two limitations of lean production.

Any two of: dependence on reliable suppliers; no buffer stock for demand surges; time and cost of culture change and training; may not suit all businesses.

An activity lasts 5 days, the EST of its start node is 6, the EST of its end node is 13 and the LFT of its end node is 15. Calculate its total and free float.

Total float = 15 − 5 − 6 = 4 days; free float = 13 − 5 − 6 = 2 days.

What is the critical path?

The sequence of activities with no float, which determines the minimum project duration; any delay to them delays the whole project.

Now practise it

Try the 31 past paper questions on Operations strategy, with mark schemes. Start with the most recent ones; if one goes wrong, come back to the section above that covers it.

Practise Operations strategy questions →