Once a business knows its direct costs and overhead absorption rates, it needs to apply them to what it actually produces. How it does this depends on the kind of work: a continuous flow of identical products (unit costing), one-off orders made to a customer’s specification (job costing), or a quantity of identical items made together (batch costing). The same principles apply to service businesses.
| Method | Used when | Examples |
|---|---|---|
| Unit costing | Many identical units are produced continuously | A bottling plant, a brick-maker; a hotel (cost per room-night), a bus company (cost per passenger-kilometre) |
| Job costing | Each order is different and is costed separately | A builder, a kitchen fitter, a printer of wedding invitations, a garage repair, an accountant’s client work |
| Batch costing | A set number of identical items is made in one run | A bakery (a batch of 500 rolls), a clothing maker, a printer of brochures |
Unit costing
Cost per unit = total costs for the period ÷ number of units produced
In May a factory made 15,000 bottles of sauce. Costs: direct materials $42,000, direct labour $27,000, production overheads $21,000. Cost per bottle = 90,000 ÷ 15,000 = $6.00.
A service example: a 60-room hotel was 75% full in a 30-day month: 60 × 30 × 75% = 1,350 room-nights. Costs for the month were $81,000, so the cost per occupied room-night = 81,000 ÷ 1,350 = $60. If rooms are let at $85 a night, each room-night earns $25 over cost. The cost unit for a service must measure what the customer actually buys.
Job costing
- Direct materials: materials issued from stores to the job (priced by FIFO or AVCO), less any returned to stores, plus any bought specially for the job.
- Direct labour: hours recorded on time sheets for the job × each worker’s rate.
- Direct expenses: costs incurred only for this job (hire of special equipment, a subcontractor).
- Prime cost = 1 + 2 + 3.
- Production overheads absorbed at the OAR × the job’s hours.
- Total production cost; add administration, selling and distribution overheads (often a percentage of production cost) for the total cost.
- Add the profit to find the price. Read carefully: a mark-up is a percentage of cost; a margin is a percentage of the selling price (price = cost ÷ (1 − margin)).
FitRight fits kitchens. Job 207: materials issued $3,450, of which $188 were returned to stores unused; a fitter worked 40 hours at $18 an hour and an electrician 12 hours at $24; a skip was hired for the job for $150. Production overheads are absorbed at $15 per direct labour hour. Administration and selling overheads are 10% of production cost. FitRight wants a profit margin of 20% of the selling price.
| Job cost sheet: Job 207 | $ | $ |
|---|---|---|
| Direct materials (3,450 − 188 returned) | 3 262 | |
| Direct labour: fitter 40 hours × $18 | 720 | |
| electrician 12 hours × $24 | 288 | 1 008 |
| Direct expenses: skip hire | 150 | |
| Prime cost | 4 420 | |
| Production overheads (52 hours × $15) | 780 | |
| Total production cost | 5 200 | |
| Administration and selling (10%) | 520 | |
| Total cost | 5 720 | |
| Profit (20% of selling price) | 1 430 | |
| Selling price (5,720 ÷ 0.80) | 7 150 |
Check: profit 1,430 ÷ price 7,150 = 20% margin, which is the same as a 25% mark-up on cost (1,430 ÷ 5,720). If the question had asked for a 20% mark-up, the price would be 5,720 × 1.2 = $6,864.
Batch costing
The whole batch is costed like a job; then the cost per unit = batch cost ÷ number of units in the batch. Costs that arise once per batch, such as setting up the machines, are spread over every unit, so bigger batches usually give a lower cost per unit.
PrintCo prints brochures. Each run needs a set-up costing $240; paper costs $0.30 and ink $0.10 per brochure; labour is $20 an hour and machine overheads are absorbed at $35 a machine hour.
| Batch cost | 2,000 brochures $ | 5,000 brochures $ |
|---|---|---|
| Set-up of the press | 240 | 240 |
| Paper ($0.30 each) | 600 | 1 500 |
| Ink ($0.10 each) | 200 | 500 |
| Direct labour (6 hours; 12 hours × $20) | 120 | 240 |
| Machine overhead (4 hours; 9 hours × $35) | 140 | 315 |
| Total batch cost | 1 300 | 2 795 |
| Cost per brochure ($) | 0.65 | 0.56 (0.559) |
A customer ordering 2,000 brochures at a 40% mark-up would pay 1,300 × 1.4 = $1,820 ($0.91 each). In the larger batch the $240 set-up is spread over 5,000 brochures instead of 2,000, which is the main reason the cost per brochure falls from $0.65 to about $0.56.
Common errors: forgetting to deduct materials returned to stores; absorbing overheads on the wrong hours; applying the profit percentage to cost when the question gives a margin on selling price; and dividing a batch cost by the wrong number of units (for example, before deducting faulty units that can’t be sold, if the question says so).
Answering the Paper 1 and 2 questions
Typical questions: “Prepare a job cost sheet and calculate the selling price”; “Calculate the cost per unit of the batch”; “State a suitable cost unit for a hotel”; or “Advise whether the business should accept the customer’s order at the price offered.”
Paper 1 has 30 multiple-choice questions: work each one out on paper before you look at the options, because the wrong options are the answers you get from the common mistakes. Paper 2 has four structured questions (30, 15, 15 and 30 marks): you prepare accounts and calculations, then explain, discuss or advise. The written parts are marked on knowledge, analysis and evaluation. Plan every “discuss”, “advise” or “evaluate” answer in the same five steps, in this order:
- Knowledge: state which costing method suits the business and define the cost unit, prime cost and total cost.
- Application: build the cost from the figures given, in the order of the job cost sheet, and apply the mark-up or margin correctly.
- Analysis: explain the result: for example, a larger batch spreads the fixed set-up cost over more brochures, cutting the cost per unit from $0.65 to $0.56.
- Evaluation: consider how reliable the figures are (estimated hours, absorption rates based on budgets) and non-financial factors such as the customer relationship and capacity.
- Conclusion: reach a clear judgement, for example: PrintCo should offer a lower price per brochure for orders of 5,000, because its own cost per unit falls and it would win larger orders.
Check yourself
A job uses materials of $800, labour of 20 hours at $16, and overheads absorbed at $10 per labour hour. What is the production cost?
800 + 320 + 200 = $1,320.
Total cost of a job is $2,400. What is the price with (a) a 25% mark-up, (b) a 25% margin?
(a) 2,400 × 1.25 = $3,000; (b) 2,400 ÷ 0.75 = $3,200.
A batch of 400 cakes costs $260. What is the cost per cake?
$0.65.
Give a suitable cost unit for a bus company and for a hospital.
Bus company: passenger-kilometre (or journey). Hospital: patient-day (or bed-night).
Why does the cost per unit usually fall as batch size increases?
Set-up costs (and other costs fixed per batch) are spread over more units.
Now practise it