Capacity utilisation and outsourcing Revision notes

Unit 4: Operations management · Chapter 25 · about 8 minutes · written for the 9609 syllabus · last checked 2026-11-18

A business that has invested in a factory, a hotel or a fleet of buses wants to use it well. This chapter covers how fully a business uses its capacity, what happens when it has too little or too much work, and outsourcing as a way of adjusting. Paper 2 often asks you to calculate capacity utilisation and then judge whether outsourcing is the right solution.

Capacity utilisation

Capacity: the maximum output a business can produce in a period with its existing resources. Capacity utilisation: current output as a percentage of maximum capacity.

capacity utilisation (%) = current output ÷ maximum possible output × 100

Example: a bakery can bake 8,000 loaves a week but bakes 6,000: capacity utilisation = 6,000 ÷ 8,000 × 100 = 75%. Its fixed costs are $24,000 a week, so fixed cost per loaf = 24,000 ÷ 6,000 = $4.00. At full capacity it would be 24,000 ÷ 8,000 = $3.00.

Operating under capacity

Low capacity utilisation means fixed costs (rent, machinery, salaried staff) are spread over fewer units, so unit costs are higher and profit margins lower. Workers may be underused and worried about their jobs, and an image of an empty restaurant or half-full hotel can put customers off. On the plus side, spare capacity means the business can meet sudden increases in demand and has time for maintenance and training.

Operating at or over maximum capacity

High utilisation spreads fixed costs widely and lowers unit costs. But working at or close to 100% for long periods brings problems: machines aren’t maintained and break down; staff are overworked, so stress, mistakes and absence rise; quality and customer service may fall; and the business has to turn away orders, possibly losing customers to rivals. Many businesses aim for a high but not total utilisation, around 85–90%.

Utilisation above 100% isn’t a calculation error in exam data: it means the business is producing more than its normal maximum, for example through overtime or extra shifts, which can only be kept up for a short time.

Improving capacity utilisation

If capacity is underused:

  • Increase demand: more promotion, lower prices in quiet periods (off-peak offers), new markets or new products that use the spare capacity.
  • Reduce capacity (rationalisation): sell or close unused buildings and machinery, reduce staff, or rent out spare space. This raises utilisation but may leave the business unable to meet future growth.
  • Take on work for other businesses, such as producing under another firm’s brand.

If the business is over capacity: increase capacity by investing in new equipment or premises, use overtime and extra shifts in the short term, or outsource some work.

Outsourcing

Outsourcing (subcontracting): using another business to carry out activities that were, or could be, done within the business itself, such as manufacturing components, cleaning, delivery, payroll or customer service.

AdvantagesDisadvantages
Lower costs when the specialist can do the work more cheaplyLess control over quality and delivery times
Extra capacity without investing in new equipment or premisesProfit margin is shared with the outsourcing provider
Access to specialist skills and technologyRisk to confidentiality and reputation if the provider performs badly or behaves unethically
Flexibility: can vary the amount of work to match demandPossible redundancies and lower morale among the business’s own staff
Managers can focus on the business’s core activitiesDependence on the provider, which may raise prices or fail

Outsourcing works best for activities that aren’t central to what makes the business distinctive, where reliable specialist providers exist and quality is easy to check. Outsourcing a core activity, such as the design of a fashion brand’s products, risks losing what makes the business special.

Answering the Paper 1 and 2 questions

Typical questions: “Evaluate whether outsourcing is the most suitable way to increase NN’s production capacity”; “Analyse one advantage and one disadvantage to PP of outsourcing the manufacture of pots”; or a capacity utilisation calculation followed by an evaluation of how to improve it (Paper 2).

In Paper 1 Section B you answer one two-part essay: part (a) for 8 marks and part (b) for 12 marks. Each Paper 2 question ends with an 8-mark part and a 12-mark part. The 12-mark parts must include evaluation, and long answers are marked on knowledge, application, analysis and evaluation. Plan every long answer in the same five steps, in this order:

  1. Knowledge: define capacity, capacity utilisation and outsourcing, and give the formula.
  2. Application: calculate utilisation from the case data and identify the business’s situation: under capacity, near full or over capacity, and why.
  3. Analysis: build chains: for example, outsourcing extra production lets the business meet rising orders without buying new machines, but it loses control of quality, so faulty products could damage its reputation.
  4. Evaluation: compare outsourcing with alternatives (overtime, new equipment, raising prices), and consider whether the rise in demand is permanent, the reliability of providers, the cost difference and the importance of quality.
  5. Conclusion: make a justified judgement, for example: outsourcing is the most suitable short-term solution because the rise in demand may be temporary, but if demand keeps growing, investing in more capacity would protect quality and margins.

Check yourself

A hotel has 120 rooms and 90 are occupied. What is its capacity utilisation?

90 ÷ 120 × 100 = 75%.

Why does low capacity utilisation raise unit costs?

Fixed costs are spread over fewer units of output, so each unit carries more fixed cost.

Give two problems of operating at full capacity for a long time.

Any two of: no time for maintenance, so breakdowns; overworked, stressed staff; falling quality; orders turned away.

Give two ways to improve capacity utilisation when capacity is underused.

Any two of: increase demand through promotion or off-peak pricing; enter new markets; reduce capacity (rationalisation); take on work for other firms.

Give one advantage and one disadvantage of outsourcing.

Advantage (any one): lower cost, extra capacity, specialist skills, flexibility, focus on core activities. Disadvantage (any one): less control of quality, shared margin, reputational risk, job losses, dependence on the provider.

Now practise it

Try the 16 past paper questions on Capacity utilisation and outsourcing, with mark schemes. Start with the most recent ones; if one goes wrong, come back to the section above that covers it.

Practise Capacity utilisation and outsourcing questions →